Project Title: Thotnae Khola HP

innerImage
  • Task: Feasibility study

  • Capacity: 74 KW

  • Status: Completed

Salient Features (as per Feasibility Study Report, 2010):
Location : Thotane Khola, Bhadaure/Mamkha VDC’s, Okhaldunga District, Sagarmatha Zone, Eastern development region of Nepal
Latitude : 27°16’25” N to 27°17’20” N
Longitude : 86°35’00” E to 86°36’57” E.
Geology
Region : Lesser Himalayan Zone
Rock composed : Quartzite, Phyllite
Geotechnical zoning : Very poor to fair
Hydrology
Catchment area : 71 km2
90% firm flow in the driest month : 0.36 m3/s
Design flow (Q40) : 1.14 m3/s
Flood 1 in 100 years : 338 m3/sec
Weir
Type : boulder lined
Length : 23.85 m
Crest level : 713.00 m amsl
Intake
Type : Semi frontal intake
Number of orifice : 3
Orifice Size : 0.5 x 1.00 m (w x h)
Invert level orifice : 712.00 m amsl
Number of gates : 3
Gravel trap
Type : Surface
Length : 5.00 m (including transition)
Width : 2.3 m
Height : 3.5 m
Spillway level : 713.00 m amsl
Gravel Flushing Canal
Type : Surface
Length : 50.60 m
Breadth : 1.00 m
Height : 1.95 m
Number of gates : 1 nos.
Approach canal
Type : Reinforced concrete rectangular culvert
Length : 6.90 m
Bottom width : 2.30 m
Height : 1.76 m
Settling basin
Type : Surface
Size : 28 x 5 x 3.28 m (l x b x h)
No. of chambers : 2
No. of flushing channel : 2
Sediment Flushing Channel
Type : Surface
Length : 14.23 m
Breadth : 0.5 m
Height : 0.5 m
No. of gates : 2
Forebay
Type : Surface
Width : 5.25 m
Length : 4.1 m
Height : 2.84 m
Penstock Pipe
Material : Steel
Length : 2361 m
Internal diameter : 800 mm
Thickness : 8-16 mm
Anchor blocks : 36 nos.
Y-Bends : 1 no.
Branching : 2 pipes of 570 mm internal diameter, 21 m long
Powerhouse
Type : Surface
Length : 16.5 m
Breadth : 8.0 m
Height : 12 m (from foundation level)
Number of generating units : 2 (Two) each 340 KW
Turbine type : Horizontal Axis Francis Turbine
Installed capacity : 680 KW
Tail water level : 622.00 m amsl
Tailrace
Type : Rectangular box culvert
Height : 0.9 m
Width : 1.5 m
Length of closed duct : 11.90 m
Transmission Facilities
Transmission line length : 3 km from Powerhouse to Mathilo Bhadaure (the existing 11 KV transmission line)
Voltage level : 11 KV
Power and Energy
Gross Head : 91 m
Net Head at design discharge : 73.20 m (at design discharge)
Installed Capacity : 680 KW
Gross Annual Energy : 4.41 GWh
Net Annual energy : 4.24 GWh
Wet Energy : 3.28 GWh
Dry Energy : 0.95 GWh
Recent News
recentImage Construction Supervision and Design Support During Construction of Jum Khola Jalvidhyut Aayojana (56 MW)
Sanima Hydro and Engineering Pvt. Ltd. has signed a contract agreement with Sanima Jum Hydropower Limited on 14th February 2024 for Construction Supervision and Design Support During Construction of Jum Khola Jalvidhyut Aayojana (56 MW). Jum Khola Jalvidhyut Aayojana is a Run-of-River (RoR) project located at Dolakha District, Bagmati Province of Nepal. Geographically,… Read More »
VIEW ALL NEWS
National Projects
national

Jum Khola Jalvidhyut Aayojana
Capacity: 56 MW
Status: Ongoing